The Seattle Public Library University Branch URM Seismic Upgrade & Renovation, City of Seattle, WA #SPL-PW-2024-0611 - Conformed Specs Volume 1    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 505 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Division 00 Procurement and Contracting Requirements
Page 3 Section 000106 Project Directory
Page 5 Section 000107 Seals Pages
Page 12 Section 000110 Table of Contents
Page 18 Pre-Bid Information and Advertisement for Bid
Page 21 Section 002113 Instructions to Bidders
Page 34 Section 003100 Available Project Information
Page 35 Limited Hazardous Materials Survey Report
Page 85 Geotechnical Report
Page 135 Buy America, Buy America Act (BABAA) Contract Provision and Self-Certification
Page 137 Bid Form
Page 138 Section 004113 Bid Form
Page 142 Inclusion Plan
Page 148 Section 004100 Attachment B Bidder / Subcontractor List
Page 149 Section 004513 Supplemental Bidder Responsibility Criteria
Page 154 Work Experience Form
Page 155 Section 005213 Agreement Form
Page 158 Request for Information
Page 159 Section 006325 Substitution Request Form
Page 163 Section 006510 Subcontractor Approval Application
Page 165 Section 006522 Public Works Prevailing Wage Certification & Subcontractor List
Page 167 Section 007213 General Conditions - Stipulated Sum Single Prime Contract
Page 217 Section 007260 Modifications to the General Conditions
Page 239 Section 007300 Supplemental Conditions - Responsible Bidder Criteria
Page 244 Section 007300a Responsible Bidder Criteria Evaluation Matrix
Page 246 Section 007302 Supplemental Conditions - Multiple Contracts
Page 247 Section 007304 Supplemental Conditions - Intents and Affidavits
Page 248 Section 007306 Supplemental Conditions - ADA Compliance
Page 249 Section 007310 Supplemental Conditions - Community Workforce Agreement
Page 250 Section 007316 Insurance Requirements
Page 255 Section 007336 Social Equity in Contracting
Page 262 Section 007343 Prevailing Wage Rate Requirements
Page 269 Section 007348 Community Workforce Agreement and Priority Hire Workers
Page 274 Community Workforce Agreement
Page 310 Division 01 General Requirements
Page 311 Section 011100 Summary of Work
Page 316 Section 011111 Summary of Hazardous Materials Work
Page 319 Section 011150 Intent and Definitions of Language Used in This Manual
Page 325 Section 012500 Substitutions and Product Options
Page 329 Section 012600 Contract Modification Procedures
Page 331 Section 012910 Applications for Payment
Page 333 Section 013113 Project Coordination
Page 338 Section 013114 Communication
Page 341 Section 013119 Project Meetings
Page 346 Section 013216 Construction Schedules
Page 352 Section 013233 Photographic Documentation
Page 354 Section 013310 Submittal Procedures
Page 361 Electronic File Request
Page 362 Section 013323 Shop Drawings, Product Data, and Samples
Page 367 Section 013516 Alteration Project Procedures
Page 372 Section 013543 Hazardous Materials Discovery
Page 373 Section 013591 Historic Treatment Procedures
Page 380 Section 014100 Regulatory Requirements
Page 383 Section 014200 Reference Standards
Page 392 Section 014300 Quality Requirements
Page 398 Section 014339 Mock-Up Requirements
Page 400 Section 014523 Testing and Inspection Services
Page 405 Section 015100 Temporary Utilities
Page 410 Section 015200 Construction Facilities
Page 414 Section 015636 Security
Page 415 Section 015639 Temporary Tree Plant Protection
Page 426 Section 015701 Environmental Protection
Page 434 Section 015719 Temporary Controls and Environmental Protection
Page 438 Section 016100 Basic Product Requirements
Page 443 Section 016600 Product Storage and Handling Requirements
Page 445 Section 017123 Field Layout
Page 447 Section 017329 Cutting and Patching
Page 450 Section 017400 Cleaning
Page 454 Section 017419 Construction & Demolition Waste Management
Page 461 Section 017700 Closeout Procedures
Page 466 Section 017800 Closeout Submittals
Page 473 Section 017839 Record Documents
Page 477 Section 018113 Sustainable Building Requirements
Page 490 Figure 1 - LEED Checklist
Page 491 Figure 2 - LEED Submittal Coversheet
Page 493 Section 018119 Construction Indoor Air Quality Management
Page 500 Section 019113 General Commissioning Requirements