Catharine Blaine K-8 Electrical System Upgrades, Seattle Public Schools, Seattle, WA #B112401 - Specs    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 554 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 2 Section 000101 Project Team Directory
Page 3 Section 000107 Seals Page
Page 5 Section 000110 Table of Contents
Page 8 Section 000115 Drawing of Index
Page 9 Section 001100 Advertisement for Bids
Page 12 Section 002113 Instructions for Bidders
Page 23 Section 003000 Available Project Information
Page 25 Section 004113 Bid Form
Page 27 Official(s) Authorized to Sign for Bidder
Page 29 Attachments
Page 30 Attachment 1 Bid Price Form
Page 32 Attachment 2 Contractor's Bid Bond
Page 33 Attachment 3 Alternates Bid Form
Page 34 Attachment 4 Subcontractor Work Listing
Page 35 Attachment 5 Subcontractor Work Listing - Structural Steel & Rebar
Page 36 Agreement
Page 53 Section 006113 Performance & Payment Bond
Page 54 Section 006220 Statement of Intent to Pay Prevailing Wages
Page 55 Section 006230 Affidavit of Wages Paid
Page 56 Section 006250 Retainage Option Form
Page 57 Section 006255 Escrow Agreement
Page 61 Section 006260 Indemnification Certificate
Page 62 Section 007200 General Conditions
Page 63 AIA Document A201-2017 General Conditions of the Contract for Construction
Page 138 Section 007311 Acceptable Worksites
Page 140 Section 007319 Safety Procedures
Page 143 Section 007320 Supplemental Conditions Asbestos Abatement
Page 145 Section 007343 Wage Rates
Page 148 Section 011000 Summary of Work
Page 154 Section 011100 Summary of Hazardous Materials Work
Page 160 Good Faith Inspection Letter
Page 169 Section 012200 Unit Prices
Page 171 Section 012300 Alternates
Page 173 Section 012600 Contract Modification Procedures
Page 178 Section 012900 Applications for Payment
Page 184 Section 012973 Schedule of Values
Page 186 Section 013113 Project Coordination
Page 191 Section 013119 Meetings
Page 196 Section 013150 Project Management Communication
Page 200 Section 013216 Schedules & Reports
Page 203 Section 013300 Submittals
Page 210 Section 013313 Certificate of Compliance
Page 211 Section 013332 Certificate of No Hazardous Materials
Page 212 Section 014100 Regulatory Requirements
Page 215 Section 014216 Definitions
Page 217 Section 014219 Reference Standards
Page 222 Section 014529 Testing Laboratory Services
Page 226 Section 015000 Construction Facilities & Temporary Controls
Page 230 Section 015526 Maintenance of Traffic
Page 232 Section 016110 Materials & Equipment
Page 235 Section 016310 Approval for Substitution & Product Options
Page 238 Substitution Request Form
Page 240 Section 016510 Delivery, Storage & Handling
Page 243 Section 017125 Utility Location Requirements
Page 245 Section 017329 Cutting & Patching
Page 250 Section 017350 Alteration Project Procedures
Page 253 Section 017400 Cleaning
Page 257 Section 017419 Construction Waste Management & Disposal
Page 266 Section 017720 Contract Closeout
Page 270 Closeout Checklist for Public Works Project
Page 271 Contractor's Affidavit of Payment of Debts & Claims
Page 272 Contractor's Affidavit of Release of Liens
Page 273 Section 017736 Warranties & Bonds
Page 277 Warranty Contact List
Page 278 Subcontractor's Warranty Contact List
Page 279 Section 017740 Warranty of Work After Final Payment
Page 280 Section 017823 Operating & Maintenance Data
Page 284 Preventive Maintenance Inventory Sheet
Page 286 Section 017839 Project Record Documents
Page 288 Section 024119 Selective Demolition
Page 290 Section 028213 Asbestos Abatement
Page 311 Section 028300 Heavy Metals Related Activities
Page 325 Section 061000 Rough Carpentry
Page 328 Section 079200 Joint Sealants
Page 332 Section 081113 Hollow Metal Doors & Frames
Page 339 Section 084113 Aluminum-Framed Entrances
Page 349 Section 087100 Door Hardware
Page 364 Section 088000 Glazing
Page 373 Section 092116 Gypsum Board Assemblies
Page 379 Section 095123 Acoustical Ceiling Systems
Page 382 Section 099000 Painting
Page 387 Section 099113 Exterior Painting
Page 393 Section 200200 Operation & Maintenance Manual for Mechanical
Page 395 Section 200500 Common Work Results for Mechanical
Page 417 Section 200503 Existing Systems Work for Mechanical
Page 422 Section 200519 Piping Specialties for Mechanical
Page 427 Section 200529 Hangers & Supports for Mechanical
Page 437 Section 200530 Sleeves & Seals for Mechanical
Page 445 Section 200593 Testing, Adjusting, Balancing for Mechanical
Page 452 Section 200700 Mechanical Insulation
Page 463 Section 200800 Commissioning of Mechanical Systems
Page 466 Section 232000 Steam & Condensate Piping
Page 474 Section 233300 Duct Accessories
Page 479 Section 233700 Air Outlets & Inlets
Page 483 Section 237223 Energy Recovery Ventilator
Page 487 Section 238239 Cabinet Heaters
Page 490 Section 255000 Integrated Automation Facility Controls
Page 501 Section 259000 Integrated Automation Control Sequence
Page 505 Section 260100 Electrical General Requirements
Page 515 Section 260200 Operation & Maintenance Manual
Page 517 Section 260300 Electrical Demolition
Page 519 Section 260400 Existing Electrical Systems
Page 524 Section 260500 Basic Materials & Methods
Page 532 Section 260526 Grounding & Bonding
Page 534 Section 262000 Electrical Distribution
Page 544 Section 262729 Fans
Page 547 Section 264300 AC Surge Suppression Below 600 Volts
Page 550 Section 321313 Concrete Paving, Curbs & Walks