Everett 36th Street CSO Storage Facility Improvements, City of Everett, WA #UP-3765-2
$30,880,000
Low Bid:
| Bids Received: 8 | ||
| Apparent Low Bid | Interwest Construction , Inc | $ 20,955,622.10 |
| 2nd | Prospect Construction Inc | $ 21,361,179.48 |
| 3rd | McClure and Sons, Inc | $ 21,779,996.29 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Everett
2930 Wetmore
Everett, WA 98201
Issued by:
www.bxwa.com
Prebid: 10/27 @ 10:30 am, 2701 36th Street, Everett, WA 98201
Notes:
City of Everett “Design and Construction Standards and Specifications” (latest edition), as found online on the City’s Website at:
https://everettwa.gov/1531/Design-Construction-Standards
Links to searchable PDFs:
Specifications: https://www.everettwa.gov/DocumentCenter/View/44265
Drawings: https://www.everettwa.gov/DocumentCenter/View/44266
Description:
The project includes, but is not limited to, constructing a 1.8 million gallon combined sewer storage tank, including construction of the tank, site preparation, site grading, construction of associated facilities including but not limited to piping (48-inch to 18-inch diameter), pumps, electrical, C2 water system and site restoration, and performing all other work as required by the contract. The project site is located near the northwest corner of 36th Street and Smith Avenue in Everett WA on the vacant portion of 3600 Smith Avenue.