Water Main Replacement “Y” - Phase 2 (Re-Bid), City of Everett, WA #UP-3814
$2,267,000
Low Bid:
| Bids Received: 5 | ||
| Apparent Low Bid | Interwest Construction, Inc | $ 2,020,202.02 |
| 2nd | Stellar J Construction | $ 2,393,578.04 |
| 3rd | Laser Underground & Earthwork, Inc | $ 2,542,668.38 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Everett
2930 Wetmore
Everett, WA 98201
Issued by:
www.bxwa.com
Description:
The project includes, but is not limited to, furnishing all labor, materials and equipment necessary to construct approximately 1,020 linear feet of 12-inch ductile iron watermain and appurtenances, including relocation of an existing PRV station, site restoration, installation of water main in 18-inch casing on the existing I-5 bridge structure over the Snohomish River and BNSF Railroad, and removal and disposal of the existing 8-inch waterline on the I-5 bridge, and performing all other work as required by the contract.