Taxiway A Rehabilitation and Associated Improvements, City of Renton, WA #CAG-25-098 - Phase 1 Plans
G0.1 Cover Sheet
G0.2 Sheet Index & Bid Schedule Descriptions
G1.1 Site & Survey Control Plan
G2.1 Construction Safety & Phasing Overview
G2.2 Construction Safety & Phasing Overview
G2.3 Construction Safety and Phasing Notes & Details
G2.4 Construction Safety and Phasing Notes & Details
G2.5 Construction Safety & Phasing - Work Area 1 and R1
G2.6 Construction Safety & Phasing - Work Area 2
G2.7 Construction Safety & Phasing - Work Area 3A, 3B and R3
G2.8 Construction Safety & Phasing - Work Area 4, R4, 5 and R5
G2.9 Construction Safety & Phasing - Work Area F1 and F2
C0.1 Pavement Demolition Plan
C0.2 Pavement Demolition Plan
C0.3 Pavement Demolition Plan
C0.4 Pavement Demolition Details
C0.5 Pavement Demolition Details
C1.1 Taxiway A Plan & Profile
C1.2 Taxiway A Plan & Profile
C1.3 Taxiway A & A1 Plan & Profile
C1.4 Taxiway A2 Plan & Profile
C1.5 Taxiway A3 Plan & Profile
C1.6 Taxiway A4 Plan & Profile
C1.7 Taxiway A5 Plan & Profile
C1.8 Paving Details
C1.9 Paving Details
C1.10 Paving Details
C1.11 Paving Details
C1.12 Paving Details
C1.13 Paving Details
C1.14 Paving Details
C2.1 Grading Plan
C2.2 Grading Plan
C2.3 Grading Plan
C2.4 Grading Plan
C2.5 Grading Plan
C2.6 Grading Plan
C2.7 Mill and Overlay Plan - West Apron
C2.8 Mill and Overlay Plan - West Apron
C2.9 Mill and Overlay Plan - West Apron
C2.10 Mill and Overlay Plan - West Apron
C2.11 Mill and Overlay Plan - West Apron
C2.12 Mill and Overlay Plan - West Apron
C2.13 Mill and Overlay Plan - Taxiway A5
C2.14 Mill and Overlay Plan - Taxiway A4
C2.15 Mill and Overlay Plan - Taxiway A3
C2.16 Mill and Overlay Plan - Taxiway A2
C2.17 Taxiway A Grading Sections
C2.18 Taxiway A Grading Sections
C2.19 Taxiway A Grading Sections
C2.20 Taxiway A Grading Sections
C2.21 Taxiway A Grading Sections
C2.22 Taxiway A Grading Sections
C2.23 Taxiway A Grading Sections
C2.24 Taxiway A & A7 Grading Sections
C3.1 Pavement Marking Plan
C3.2 Pavement Marking Plan
C3.3 Pavement Marking Plan
C3.4 Pavement Marking Details
C3.5 Pavement Marking Details
C3.6 Pavement Marking Details
C5.1 Erosion Control Plan
C5.2 Erosion Control Plan
C5.3 Erosion Control Plan
C5.4 Erosion Control Details
C5.5 Erosion Control Details
C5.6 Erosion Control Details
C6.0 Storm Drainage General Notes
C6.1 Storm Drainage Improvements Plan
C6.2 Storm Drainage Improvements Plan
C6.3 Storm Drainage Improvements Plan
C6.4 Underdrain Plan
C6.5 Underdrain Plan
C6.6 Underdrain Plan
C6.7 Storm Plan & Profile
C6.8 Storm Plan & Profile
C6.9 Storm Plan & Profile
C6.10 Storm Plan & Profile
C6.11 Storm Plan & Profile
C6.12 Storm Plan & Profile
C6.13 Storm Plan & Profile
C6.14 Storm Plan & Profile
C6.15 Storm Details
C6.16 Storm Details
C6.17 Storm Details
C6.18 Storm Details
C7.1 Water Improvements Plan
C7.2 Water Improvements Plan
C7.3 Water Improvements Plan
C7.4 Water Improvements Plan
C7.5 Water Improvements Plan
C7.6 Water Details
C7.7 Water Details
E0.1 Electrical Scope of Work Plan
E1.1 Electrical Demolition Plan
E1.2 Electrical Demolition Plan
E1.3 Electrical Demolition Plan
E2.1 Electrical Lighting and Signage Plan
E2.2 Electrical Lighting and Signage Plan
E2.3 Electrical Lighting and Signage Plan
E2.4 Electrical Lighting and Signage Fixture Tables
E3.1 Electrical Details
E3.2 Electrical Details
E3.3 Electrical Details
E3.4 Electrical Details
E3.5 Electrical Details
E3.6 Electrical Details
E4.1 Airfield Lighting Vault Demolition Plan
E4.2 Airfield Lighting Vault Reconfiguration Plan
E4.3 Schedule D - New Airfield Lighting Vault Building Plan
E4.4 Schedule D - New Airfield Lighting Vault Equipment Plan
E5.1 Taxiway A Circuit Map