2026 City Center CIPP Project, City of Renton, WA #CAG-26-124
$2,000,000 to $2,250,000
Volume 1 Specs
Volume 2 CIPP Table & Site Maps
Addendum #1 - Revised
Addendum #2
Schedule of Prices Clarification 7/7/2026
Register on this project.
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Renton
1055 South Grady Way
Renton WA 98055
425-430-7200
Contact: Jesse Newman
425-430-7211
jnewman@rentonwa.gov
Issued by:
www.bxwa.com
Description:
Schedule A – General Items
- Mobilization
- Temporary traffic control measures following the Contract Documents and applicable City of Renton and MUTCD standards.
- Apprenticeship Utilization Requirements
Schedule B – Sewer Items
- Cured-in-Place-Pipe (CIPP) Rehabilitation of a combined total of approximately 13,185 LF (LF) of 6”, 8”, 10”, and 15” Sanitary Sewer pipe.
- Trim 9 intruding laterals.
- Reinstatement of 200 side-sewer laterals
- Deep Clean of one lateral, and install of a Short-Range Lateral Seal (1-2 ft)
- Point Repairs (as necessary)
- CIPP Performance testing and analysis, 13 tests
Schedule C – Storm Items
- CIPP Rehabilitation of a combined total of approximately 4,149 LF of 12”, 15”, and 24” diameter storm pipe.
- Reinstatement of 28 storm-sewer laterals
- Trim 22 intruding laterals.
- Point Repairs (as necessary)
- CIPP Performance testing, 4 tests
Schedule B and C
- Confirm the diameter and length of sewer and storm pipes to be CIPP Rehabbed
- Confirm Storm and Sewer Lateral Location
- Pre- and post-cleaning and Inspection
- Bypass pumping