Orchard Avenue Water Main Replacement Project, City of Gold Bar, WA #24001575
$830,000 to $870,000
Low Bid:
| Bids Received: 11 | ||
| Apparent Low Bid | D&G Backhoe | $ 742,031.83 |
| 2nd | B&L Utility | $ 818,959.15 |
| 3rd | Raw Land Construction | $ 820,118.88 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of Gold Bar
107 5th Street
Gold Bar, WA 98251
360-793-1101
Contact: Denise Beaston
d.beaston@cityofgoldbar.us
Issued by:
www.bxwa.com
Engineer:
Atwell, LLC
25 Central Way Suite 400
Kirkland, WA 98033
Contact: Taylor Brown, PE
425-365-3679
Description:
The work to be performed is as follows: The work to be performed under these specifications consists of furnishing all labor, tools, materials, and equipment necessary for construction of the Orchard Ave Water Main Replacement Project. Generally, the project includes the construction of ±2,630 lineal feet of new 8-inch DI water main and ±250 lineal feet of new 6-inch DI water main with associated valves, fittings, fire hydrants, air and vacuum release valves, and water services. It also includes traffic control, trench repair, and associated project restoration as shown on the Contract Plans, these Contract Provisions, and the Standard Specifications.