Meadowbrook Improvement, City of North Bend, WA
$10,200,000
Low Bid:
| Bids Received: 4 | ||
| Apparent Low Bid | Northwest Construction, Inc. | $ 10,297,755.89 |
| 2nd | Marshbank Construction, Inc. | $ 10,865,329.61 |
| 3rd | Fury Site Works, Inc. | $ 12,668,528.10 |
| 4th | James W Fowler Co. | $ 14,450,069.87 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
City of North Bend
920 SE Cedar Falls Way
North Bend, WA 98045
Contacts:
Tom Mohr, PE
tmohr@northbendwa.gov
Issued by:
www.bxwa.com
Description:
The project scope of work consists of the following four schedules of work:
Schedule A – Sanitary Sewer ULID No. 7: The work includes the construction of sewer pipe to support a future low-pressure grinder pump system, to include approximately 12,400 LF of HDPE sewer force main ranging in sizes of 2-inch to 8-inch, 40 valves ranging in sizes of 2-inch to 8-inch, 43 low-pressure sewer services, 40 locate stations, auger boring three 30-inch steel casings totaling 260 LF, 1,030 LF of 8-inch PVC gravity sewer main, 13 48-inch manholes, 21 sewer cleanouts, a duplex grinder pump station including emergency standby generator, and associated surface restoration. In addition, the schedule will provide for the installation of a 3-inch force main by directional drilling, and installation of force main across two existing bridges.
Schedule B – NW 14th Street Water Main: The work includes the construction of approximately 1,500 LF of 12-inch DI Water Main, auger boring 145 LF of 30-inch steel casing, four fire hydrant assemblies, three 12-Inch Gate Valves, 16 water services, and associated surface restoration.
Schedule C – NW 14th Street Roadway Improvements: The work includes the reconstruction of approximately 1,000 LF of roadway consisting of approximately 3,400 SY of cement treated base, and 610 tons of HMA.
Schedule D – NW 8th Street Water Main: The work includes the construction of approximately 2,700 LF of DI water main ranging in sizes of 8-inch to 20-inch, auger boring two 30-inch steel casings totaling 125 LF, four fire hydrant assemblies, 13 12-inch gate valves, five water services, and associated surface restoration. In addition, the schedule will provide installation of a water main across an existing bridge.