Page 1 Cover Page
Page 2 Table of Contents
Page 4 Instructions to Bidders
Page 21 Public Works Bid Proposal
Page 25 Non-Collusion Declaration
Page 26 Part 2 - Mandatory Bidder Responsibility Checklist
Page 28 Part 3 - Mandatory Subcontractor Responsibility Checklist
Page 30 Part 4 - Supplemental Bidder Certifications
Page 32 Part 5 - Certification of Compliance with Wage Payment Statutes
Page 33 Part 6 - List of Completed Projects
Page 36 Part 7 - Public Works Contract
Page 46 Exhibit A Summary of Work
Page 49 Exhibit B Performance and Payment Bonds
Page 50 Section 1 Performance Bond
Page 53 Section 2 Payment Bond
Page 57 Exhibit C Approved Permits
Page 58 Exhibit D Engineering and Construction Specifications
Page 64 Exhibit E Owner-Supplied Contract Drawings (Under Separate Cover)
Page 65 Exhibit F Design Report
Page 66 Exhibit C Permits
Page 104 Construction Inspection Plan
Page 109 USDA-NRCS Construction Specifications
Page 156 Project Design Report