Main Pump Station Improvements, City of Camas, WA #SWR24003B - Specs    

Order Prints   FastBid 3 Help  

FastBid requires JavaScript to run. Please call 425-258-1303 for more information.

This document has 446 pages. Here are the ones with descriptions:
Click on any to load whole document, opened to the selected page.
Then use the sheet list navigation buttons to load the other pages.

Page 1 Cover Page
Page 3 Table of Contents
Page 4 Call for Bids
Page 7 Part One Bidding Documents
Page 8 Bidder's Information Page
Page 9 Proposal
Page 11 Mandatory Bidder Responsibility Criteria Information
Page 12 Verification of Subcontractor Responsibility Criteria
Page 13 Bidder's Checklist
Page 15 Acknowledgement of Contractor Lawful Hiring Compliance Enrollment
Page 16 Non-Collusion Declaration
Page 17 Bid Bond Acknowledgement
Page 18 Local Agency Subcontractor List
Page 20 Part Two Contract Documents
Page 21 Contract
Page 24 Declaration of Option for Investment of Retained Percentage
Page 25 Contract Bond
Page 27 The United States Department of Transportation - Appendix A of the Standard Title VI / Non-Discrimination Assurances
Page 29 The United States Department of Transportation - Appendix E of the Standard Title VI / Non-Discrimination Assurances
Page 31 Part Three Affidavit of E-Verify Compliance
Page 33 Part Four Amendments to the Standard Specifications
Page 35 Part Five Special Provisions
Page 36 Introduction to the Special Provisions
Page 37 Division 1 General Requirements
Page 57 Division 2 Earthwork
Page 58 Division 7 Drainage Structures, Storm Sewers, Sanitary Sewers, Water Mains, and Conduits
Page 60 Part Six CSI Technical Specifications
Page 61 Section 000105 Certificate of Engineer
Page 64 Section 011000 Summary of Work
Page 65 Section 012000 Measurement and Payment
Page 69 Section 013100 Project Management and Coordination
Page 72 Section 013219 Submittals
Page 81 Section 014000 Quality Requirements
Page 84 Section 014333 Manufacturer's Field Services
Page 88 Section 015100 Temporary Utilities and Facilities
Page 92 Section 015139 Temporary Wastewater Pumping Facilities
Page 97 Section 015525 Temporary Traffic Control
Page 102 Section 016000 Product Requirements
Page 106 Section 017600 Protection and Maintenance of Work and Property
Page 108 Section 017823 Operations and Maintenance Manuals
Page 117 Section 019110 Equipment Testing and Facility Startup
Page 122 Section 024100 Demolition
Page 124 Section 031100 Concrete Formwork
Page 128 Section 033000 Cast-In-Place Concrete
Page 137 Section 050519 Post Installed Concrete Anchors
Page 141 Section 055000 Miscellaneous Metals
Page 145 Section 083113 Access Doors and Frames
Page 147 Section 099000 Protective Coatings
Page 153 Section 099010 Galvanizing
Page 155 Section 230553 Identification for HVAC Equipment
Page 157 Section 230593 Testing, Adjusting, and Balancing for HVAC
Page 160 Section 233423 HVAC Power Ventilators
Page 164 Section 238410 Electric Heating Equipment
Page 166 Section 260500 General Requirements for Electrical Work
Page 187 Section 260505 Selective Demolition for Electrical
Page 189 Section 260519 Low-Voltage Conductors, Wires and Cables
Page 209 Section 260526 Grounding System
Page 217 Section 260529 Hangers and Supports for Electrical Systems
Page 222 Section 260533 Raceways, Boxes, and Fittings
Page 241 Section 260553 Identification for Electrical Systems
Page 254 Section 260800 Commissioning of Electrical Systems
Page 258 Section 262726 Wiring Devices
Page 264 Section 262813 Fuses
Page 271 Section 262924 Active Front End Low Voltage Adjustable Frequency Drives
Page 284 Section 263623 Automatic Transfer Switches
Page 291 Section 311100 Site Clearing
Page 293 Section 312300 Excavation and Fill
Page 300 Section 312333 Trenching, Backfilling and Compaction
Page 305 Section 330506 Hydrostatic Pressure Testing
Page 307 Section 400670 Schedules of Instrumentation for Process Systems
Page 308 Section 402700 Process Piping Systems
Page 318 Section 402900 Process Valves
Page 325 Section 406113 Process Control System General Provisions
Page 340 Section 406121 Process Control System Testing
Page 361 Section 406126 Process Control System Training
Page 365 Section 406263 Operator Interface Terminals (OIT)
Page 370 Section 406343 Programmable Logic Controllers
Page 373 Section 406716 Control Panels
Page 386 Section 406733 Panel Wiring
Page 393 Section 407113 Magnetic Flow Meters
Page 399 Section 407179 Flow Switches
Page 404 Section 407223 Radar Level Meters
Page 410 Section 407816 Indicating Lights
Page 414 Section 407819 Switches and Push Buttons
Page 418 Section 407853 Relays / Terminal Blocks
Page 425 Section 407856 Isolators, Intrinsically-Safe Barriers, and Surge Suppressors
Page 434 Section 407859 Power Supplies
Page 439 Section 408000 Commissioning of Process Systems
Page 445 Part Seven Washington State Hourly Prevailing Wage Rates
Page 446 Part Eight Reduced Size Construction Plans (Under Separate Cover)