Reservoirs 2 and 3 - Storm Drain and Ring Roads Replacement, Alderwood Water and Wastewater District, Lynnwood, WA #W2106
$1,600,000 to $1,950,000
Low Bid:
Bids Received: 10 | ||
Apparent Low Bid | Marshbank Construction, Inc. | $ 1,358,800.00 |
2nd | PELLCO Construction, Inc. | $ 1,469,213.00 |
3rd | Interwest Construction, Inc. | $ 1,564,938.00 |
View self registered Bidders List
Builders Exchange of Washington, Inc. Subs and Suppliers
Owner:
Alderwood Water Wastewater District
3626 156th Street SW
Lynnwood, WA 98087
Contact: David MacDonald
425-743-4605
dmacdonald@awwd.com
Issued by:
www.bxwa.com
Prebid: 4/10 @ 10:00 am at the Reservoirs 2 and 3 site
Description:
The work under this Contract includes, but is not limited to:
• Installation of approximately 1,300 linear feet of buried storm sewer main (various sizes).
• Installation of approximately 26 catch basins, and a CDS water quality pretreatment unit.
• Placement of approximately 1,500 tons of hot mix asphalt and 1,500 tons of crushed surfacing top course, to rehabilitate the existing pavement at Reservoirs 2 and 3 as well as provide full-depth repair of portions of the administration building parking lot.
• Installation of approximately 1,800 square yards of geotextile, and performance of crack sealing and fog sealing, as additional measures to rehabilitate the administration building parking lot.
• Trenching and installation of approximately 5,900 linear feet of conduit and appurtenances.
• Removal/abandonment of existing roadway and civil elements (including approximately 110 cable anchors and approximately 10 linear feet of roof drain asbestos pipe)