Printable Drawing List

Hazen High School Phased Modernization, Renton, WA - Exhibit A.1 - Site Logistics Plan

G010 Architectural Site Plan - Phase 0 - April 2025 - June 2025
G010 Architectural Site Plan - Phase 1 - Summer 2025
G010 Architectural Site Plan - Phase 1 - September 2025 - August 2026
G010 Architectural Site Plan - Phase 2A - Summer 2026
G010 Architectural Site Plan - Phase 2B - September 2026 - March 2027
G010 Architectural Site Plan - Phase 2C - December 2026 - August 2027
G010 Architectural Site Plan - Phase 3A - June 2027 - August 2027
G010 Architectural Site Plan - Phase 3B - September 2027 - March 2028
G010 Architectural Site Plan - Phase 4 - February 2028 - April 2029